Building Review

Review No:1

1. Plans include changes to 2 separate buildings, Buildings 1 and 2. Two change orders are required, as there are separate permits for each building. Please include two complete descriptions of work for the changes to the two buildings. See the building technicians when materials are resubmitted so that another change order may be written up for Building 2, and a more complete description for Building 1 may be included.   



2. Please submit energy compliance documents for the equipment alterations to the air conditioning system and the addition of a new water heater.



3. Please include revised mechanical and plumbing plans for the proposed changes to these systems.

 


Please indicate here if any changes have been made to the plans that are not a result of corrections from this list. Have changes made to the plans not resulting from this correction list?


Please check ____________Yes ______________No


If Yes, please describe the changes and where they are located in the plans:


Note: For the referenced code information, go to http://www.bsc.ca.gov/Codes.aspx and/or http://www.sccoplanning.com/PlanningHome/BuildingSafety/BuildingCodes.aspx .


Resubmittal Information: http://www.sccoplanning.com/Portals/2/County/Planning/bldg/Re-submittal%20Process%207.21.16.pdf


Please be advised that if plan check comments are required to be addressed leading to a 3rd plan check, additional charges will be added to your permit fee at an hourly rate.


If you have any questions regarding these building plan check comments, please contact Laura Brinson at 831-454-3151 or email laura.brinson@santacruzcounty.us.

Review No:2