Sanitation Review

Review No:1
Sanitation District Review Comments: No. 1
Date of Review: 06-17-2020
Permit #: B-202556, APN: 039-221-11
This review was based on plans submitted for the subject project entitled 150 Rancho Del Mar prepared by Johnson Lyman Architects dated 04-30-2020.

Building K

Corrections Required:

1.) Per District Ordinance Section 7.04.375 A.3.d/e, remodels/additions that increase the plumbing fixture units or the square footage of the building require that the sanitary sewer lateral be video inspected by a licensed plumber PRIOR to issuance of building permit. A copy of the video and inspection report must be uploaded to County Sanitation’s BOX drive for review. County staff will review and issue a determination of necessary sewer lateral repairs. If repairs are required, the applicant will have two options. Either:
  • Secure a separate sewer lateral repair permit (no fee) and complete required repairs PRIOR to issuance of building permit. The repairs must be inspected and approved by the Sanitation Inspector before the Building Permit will be issued.
OR
  • Resubmit plans including sufficient layout, details, and specifications for the contractor to repair the sewer lateral in accordance with the County’s issued repair requirements. The repairs must be inspected and approved by the Sanitation Inspector before the County will issue final approval of the project.

Further details regarding the sewer lateral video inspection requirements can be found here:
http://www.dpw.co.santa-cruz.ca.us/Home/SewerWater/SewerLateralResourcesandSepticAbandonment.aspx


2.) Show approximate sewer lateral layout on site plans from the structure to the connection to the public main.
  • Include cleanout locations. Cleanouts are required within 2’ of the point of exit from the building and every 100’. If existing cleanouts do not satisfy this requirement, show new cleanouts to be installed.


3.) Increased discharge will not exceed existing credit for commercial sewer connection. No further connection fees required. (NO RESPONSE REQUIRED)


Design and Construction Standards:
The project sewer design and connection of the project to the Santa Cruz County Sanitation District system will be required to conform to the County of Santa Cruz Design Criteria (CDC) Part 4, Sanitary Sewer Design, latest edition.
http://www.dpw.co.santa-cruz.ca.us/Portals/19/pdfs/DESIGNCRITERIA.pdf

Any questions regarding the above criteria should be directed to Bryan Wardlow of the Sanitation Engineering division at (831) 454-2160.
Review No:2
Sanitation District Review Comments: No. 2
Date of Review: 08-28-2020
Permit #: B-202556, APN: 039-221-11
This review was based on plans submitted for the subject project entitled 150 Rancho Del Mar prepared by Johnson Lyman Architects dated 07-09-2020.

Building K

Corrections Required:
Previous plan check comment #1 does not appear to have been addressed:

1.) Per District Ordinance Section 7.04.375 A.3.e, remodels that increase the plumbing fixture units or square footage of the structure require that the existing sanitary sewer lateral be video inspected by a licensed plumber PRIOR to issuance of building permit. A copy of the video and inspection report must be uploaded to County Sanitation’s cloud storage (on box.com) for review. County staff will review and issue a determination of necessary sewer lateral repairs.
• If repairs are required, a separate sewer repair permit shall be issued (no-fee). The repairs must be inspected and approved by the Sanitation Inspector before the County will issue final approval of the project.
• Include on the plans sufficient layout, details, and specifications for the contractor to repair the sewer lateral in accordance with the County’s issued repair requirements.
• Further details regarding the sewer lateral video inspection requirements can be found here: https://sccsd.us/sewer-lateral-program/


Design and Construction Standards:
The project sewer design and connection of the project to the Santa Cruz County Sanitation District system will be required to conform to the County of Santa Cruz Design Criteria (CDC) Part 4, Sanitary Sewer Design, latest edition.
http://www.dpw.co.santa-cruz.ca.us/Portals/19/pdfs/DESIGNCRITERIA.pdf

Any questions regarding the above criteria should be directed to Bryan Wardlow of the Sanitation Engineering division at (831) 454-2160.
Review No:3
Sanitation District Review Comments: No. 3
Date of Review: 08-18-2020
Permit #: B-202556, APN: 039-221-11
This review was based on plans submitted for the subject project entitled 150 Rancho Del Mar prepared by Johnson Lyman Architects dated 07-09-2020.

Building K

No Corrections Required:
1.) Sewer lateral video inspection was uploaded and reviewed on 08-12-2020. No work required at this time. (NO RESPONSE REQUIRED).

2.) Increased discharge will not exceed existing credit for commercial sewer connection. No additional connection fees required. (NO RESPONSE REQUIRED)


Design and Construction Standards:
The project sewer design and connection of the project to the Santa Cruz County Sanitation District system will be required to conform to the County of Santa Cruz Design Criteria (CDC) Part 4, Sanitary Sewer Design, latest edition.
http://www.dpw.co.santa-cruz.ca.us/Portals/19/pdfs/DESIGNCRITERIA.pdf

Any questions regarding the above criteria should be directed to Bryan Wardlow of the Sanitation Engineering division at (831) 454-2160.