B-235038_2023-09-20_1st
Review by Thomas Pallinger Responses must include an annotated copy of these comments and indicate the specific sheet/drawing numbers where revisions are located. Text can be copied from the Application Status webpage and pasted into a text editing program. https://sccounty01.co.santa-cruz.ca.us//PlanningapplicationStatus/ Please Respond: Have changes been made in addition to those resulting from the Building Review Comments? ___________ (Yes or No). If yes, please briefly describe the additional changes and the location on the plans/documents: Please address the following comments: 1. If a licensed architect or engineer has provided a design, a signed stamp must be on each sheet representing their work. 2. Sheet
CVR: The Sheet Index does not match this plans submittal. Ensure each sheet is identified
in the Index prior to resubmittal. 3. Sheet
CVR: Include the County of Santa Cruz Amendments under the “Applicable Codes”. 4. Sheet
CVR: Specify the occupancy classification R-3 under the “Project Data”. 5. Sheet
CVR: Note a minimum of 65% demolition and construction waste shall be recycled.
(CRC R334.1) 6. Sheet
CVR: This building appears to be located in a High Fire Severity Zone designated
by the OSFM. Note this information under the “Project Data”. 7. Sheet
A1: Show the minimum front, side, and rear building setbacks to each lot line. 8. Sheet
A1: Show the North orientation arrow on the plan. The “Site Vicinity” map does
not provide sufficient information for plan review. 9. Sheet
A-1: Note storm water protection measures shall
be implemented at the initial stage of construction activity through the use of
a barrier system, wattle, or other approved method. (CalGreen 4.106.2) 10. Sheet
A1: Show 5% directional arrows away from foundation walls where impervious
surfaces are not provided within 10’ of the building. (CRC R401.3) 11. Sheet
A1: Show the size and location of the new water meter and show the size and
route of water pipe to the ADU. If supply is taken from the residence, show the
total number of drainage fixture serving each building and justify the residences
water pipe is adequately sized for supply and distribution to each building.
(CPC 610.3 and 610.4) 12. Sheet
A1: Show where the LPG tank is located and show the gas pipe size, length, and
material type to the ADU. (See the CPC Section 1215.1 for the minimum size
based on the material type, pipe length, and pressure drop) 13. Sheet
A1: Show the point of connection to the serving electric utility and show the
route of feeders to the ADU. 14. Sheet
A1: Show where the existing septic tank and leach lines are located. 15. Sheet
A1: Show a 3” minimum sanitary sewer lateral between the septic tank and ADU
and provide a 2-way cleanout to grade at the lower end of the drainage pipe. (CPC
719.1) 16. Sheet
A-2: Show tempered glazing in the 2040 window adjacent to the front door. (CRC
R308.4.2(1)) 17. Sheet
A-2: Show tempered glazing in the 3040 master bathroom window. Additionally, show
tempered glazing in the 3020 shower area window if the bottom exposed edge is
less than 60” off the floor. (CRC R308.4.5) 18. Sheet
A-2: The garage shall be separated from the dwelling and its attic space by not
less than 1/2" gypsum board applied to the garage side of the common walls
and ceiling. (CRC R302.6) 19. Sheet
A-2: Doors that separate the garage from dwelling shall be solid core wood or
honey comb steel, or 20-minute fire rated, and equipped with a self-closing and
self-latching device. (CRC R302.5.1) 20. Sheet
A-2: Show the area of floor used for parking of automobiles sloped to
facilitate the movement of liquids toward the main vehicle doorway. (CRC R309) 21. Sheet
A-2: Submit details that illustrate reinforcement for the installation of
future grab bars at one water closet and one bathtub or
shower location. (CRC R327.1.1) 22. Sheet
A-2: Show an attic access not less than 22”x 30” in a readily accessible
location. (CRC R807.1) 23. Sheet
A-3: Show the following roof ventilation calculations, (1200/150=8sf.) on the
plan and specify the size and minimum number of ventilators required. (CRC
R806.2) 24. Sheet
A-3: Roof top vents shall have screen openings not less than 1/16” and no
greater than 1/8” constructed of non-combustible material. Additionally, remove
notation to the “Turbine Vents” unless they meet the requirements for wildfire
exposure and are listed on the OSFM’s approved materials list. (CRC R337.6) https://osfm.fire.ca.gov 25. Sheet
A-3: Roof covering materials shall have a Class
“A” fire resistance-rating. (CRC R337.5) 26. Sheet
A-3: Valley flashing, if provided, shall be not less than 26 gage over one
layer of 72-pound mineral-surfaced cap sheet at least 36 inches wide. (CRC R337.5.3)
27. Sheet
A-3: Roof gutters shall be provided with the means to prevent the accumulation
of leaves and debris in the gutter. (CRC R337.5.4) 28. Sheet
A-4: Roof Eaves and Soffits shall be non-combustible material,
ignition resistant material or one layer of 5/8” Type X exterior rated gypsum
sheathing applied behind an exterior covering on the underside of the eave or
soffit. (CRC R337.7.5) 29. Sheet
A-4: Exterior porch ceilings shall be non-combustible
material, ignition resistant material, one layer of 5/8” Type X exterior rated
gypsum sheathing applied behind an exterior covering on the underside of the
porch ceiling, or an assembly approved by the OSFM. (CRC R337.7.7) 30. Sheet
A-4: Exterior siding shall be either non-combustible material, ignition
resistant material, one layer of 5/8” Type X exterior rated gypsum sheathing applied
behind an exterior covering, or an assembly approved by the OSFM. (CRC R337.7.3) 31. Sheet
A-4: Exterior windows and glazed door assemblies shall be constructed with a
minimum of one pane of tempered glass or not less than a 20-minute fire
resistance rating. The exterior door surface shall be
non-combustible or fire-resistant, or 1-3/8” solid core wood. Raised panels shall
be a minimum 1-1/4” thick tapering to not less than a 3/8” tongue. (CRC
R337.8) 32. Sheet
A-4: The exterior garage door shall resist the intrusion of embers from
entering by preventing gaps between doors and door openings, at the bottom, sides,
and tops of doors, from exceeding 1/8”. Gaps between doors and door openings
shall be controlled by one of the following methods, (a) Weatherstripping materials that have been
tested in accordance with ASTM D638, (b) Door overlaps onto jambs
and headers, (c) Garage door jambs and headers covered with metal
flashing. (CRC R337.8.4) 34. Sheet A-4: Verify if the ADU will be
assigned a separate building address. If so, show the approximate location at
the front of the building with approved identification signage, and submit a
completed and signed County of Santa Cruz Street Addressing Service Request
Form. (CRC R319) 35. Sheet A-5: Submit details that
illustrate how roof ventilation air will be allowed to flow between enclosed
rafter bays and exhausted at the upper and lower roof vents. (CRC R806.1) 36. Mechanical
Comment: Review and revise all outdated “Mechanical Plan Check Notes” to show
compliance with the current 2022 code cycle. 37. Mechanical
Comment: Show the location of an indoor quality fan not less than 57 cfm.
(Title24 Pg.11/12) 38. Mechanical
Comment: Show a kitchen exhaust hood not less than 100 cfm. (CMC Table 403.7) 39. Mechanical
Comment: The Title24 certificate of compliance requires a VCHP heat pump
appliance without ducting. Remove all registers, return air grille, and ducting
from Sheet M-1 and show the location of all air handlers and the heat pump.
(Title24 Pg.10/12) 41. Electrical
Comment: Electrical outlets, switches, and controls shall be located not more
than 48" to the top of the outlet box and not less than 15" measured
from the bottom of the outlet box above the finished floor. Revise all plans
accordingly. (CRC Section R327.1.2) 42. Electrical
Comment: Show dedicated 240V branch circuit wiring, (50A minimum capacity)
within 36” of the kitchen cooktop, having no obstructions. (CEnC Section
150.0(u)) 43. Electrical
Comment: Show dedicated 240V branch circuit
wiring, (30A minimum capacity) within 36” of the dryer, having no obstructions.
(CEnC Section 150.0(v)) 44. Electrical
Comment: Specify the electrical requirement for the heat pump water heater, as
required by the manufacturers specifications/installation manual. 45. Electrical
Comment: Show an AC Disconnect for the HVAC
heat pump. 46. Electrical
Comment: Note the
following information for Energy Storage System Readiness and show the
approximate location where future system components will be located; A. ESS-ready
interconnection equipment with backed up capacity of 60 amps or more and four
or more ESS supplied branch circuits or; B. Dedicated
raceway from the main service to a subpanel that supplies the branch circuits;
at least four branch circuits must be identified and have their source
collocated at a single panelboard suitable to be supplied by the ESS and; C. Space must
be reserved to allow future installation of a system isolation
equipment/transfer switch within 3’ of the main panelboard, with raceways
installed between the panelboard and the switch location to allow the
connection of backup power source. (CEnC Section 150.0(s) and CRC R328.4) 47. Electrical
Comment: Show all garage outlets GFCI protected. (CEC 210.8) 48. Electrical
Comment: Provide a raceway not less than 1” diameter to accommodate a dedicated
208/240V branch circuit to facilitate future electric vehicle charging, in the
garage. (CalGreen 4.106.4) 49. Electrical
Comment: Note all luminaires shall comply with CEnC Table 150.0-A and be high
efficacy. 50. Plumbing
Comment: Remove reference to the gas utility meter and show a gas shut-off
valve at the exterior wall. Additionally, verify if the County requires an
automatic gas valve in the event of seismic activity. 51. Plumbing
Comment: Note all hot water line piping shall be insulated not less than the
pipe diameter. (CPC 609.12) 52. Plumbing
Comment: Revise Sheet P-1 to show a heat pump type water and submit
architectural details for installation of the appliance. (Title24 Pg.9/12) 53. Sheet
T24-1: Revise the fenestration/glazing square footage to 12 sf. on Pg.7/12 as
illustrated on Sheet A-2. 54. Structural
Calculations: Revise the Building and Residential Code references on Pg.5/74 to
show compliance with the current 2022 code cycle. 55. Geotechnical
Investigation, Pg.5/23: Update the “CBC Earthquake Design Criteria” code
reference to show compliance with CBC 2022 and verify if the seismic design parameters
comply with current code requirements. If so, ensure Sheet S-01 reflects any
changes under “Design Data #4”. 56. Sheet
S-01: Reference the geotechnical engineer, GeoEngineering, Inc., and Project
No. P22-270, Dated October 10, 2022, on the plan. 57. Sheet
S-01: : Revise “Special Inspection Note #1” and the “Design Data Codes” to show
compliance with the current 2022, (IBC 2021) code cycles. 58. Sheet
S-01: : Revise “General Notes #1” Building and Residential Code references, to
show compliance with the current 2022 code cycle. 59. Sheet
S-01: Submit a completed and signed County of Santa Cruz Special Inspection and
Testing Agreement form pursuant to CBC Section 1705.3 (3,000 psi Concrete
Strength) 60. Sheet
S-03: Verify if this project requires structural observation pursuant to CBC
Section 1803. If so, provide a prominent note on the plan, list what is to be
observed, and when field reports shall be submitted to the Building official. 61. Sheet
S-03: Verify
if the structural loads in this building assume a monolithic concrete pour. If
so, note accordingly on plans. If not, provide a detail for cold joint
construction. 62. Sheet
S-04: Specify mechanical connection between
Beam CB1 and CB2. Detail 12/S09 does not appear to illustrate this information. 63. Sheet
S-07, Section A: Submit details that illustrate how the 2x covered porch
rafters attach the exterior wall assembly. 64. Sheet
S-07, Section A: Submit details that illustrate how the exterior walls of the roof
dormer transfer to the double 2x roof rafters for lateral and wind uplift
loads. [End
of Comments] Note: For the
referenced code information, go to http://www.bsc.ca.gov/Codes.aspx and/or
http://www.sccoplanning.com/PlanningHome/BuildingSafety/BuildingCodes.aspx. Resubmittal Requirements: 1) “Complete sets” of plans with revisions clouded, labeled,
and keyed to a revision date list. 2) Written responses referencing revised sheet(s) and/or
detail(s). This plan check list may be copied, and responses written below each
item. 3) Supplemental documents, as required. Resubmittal Information: http://www.sccoplanning.com/Portals/2/County/Planning/bldg/Re-submittal%20Process%207.21.16.pdf Please be advised that if plan check comments are required to be addressed leading to a 3rd plan check, additional charges will be added to your permit fee at an hourly rate. If you have any questions regarding these building plan check comments, please contact CSG Consultants, Inc. at 888-794-2016, planreview@csgengr.com. B-235038_2024-11-14_2nd
Review by Thomas Pallinger Responses must include an annotated copy of these comments
and indicate the specific sheet/drawing numbers where revisions are located.
Text can be copied from the Application Status webpage and pasted into a text
editing program. https://sccounty01.co.santa-cruz.ca.us//PlanningapplicationStatus/ Please Respond: Have changes been made in addition to
those resulting from the Building Review Comments? ___________ (Yes or No). If
yes, please briefly describe the additional changes and the location on the
plans/documents: Please address the following comments: 1. If a licensed architect or engineer has provided a
design, a signed stamp must be on each sheet representing their work. PC2: This comment remains. 2. Sheet
CVR: The Sheet Index does not match this plans submittal. Ensure each sheet is identified
in the Index prior to resubmittal. PC2: This
comment remains. Please ensure each plan sheet is identified in the Index prior
to resubmittal. 3. Sheet
A1: Show the size and location of the new water meter and show the size and
route of water pipe to the ADU. If supply is taken from the residence, show the
total number of drainage fixture serving each building and justify the residence’s
water pipe is adequately sized for supply and distribution to each building.
(CPC 610.3 and 610.4) PC2: Please
show location, minimum water pipe size, and maximum pipe length between the new
water meter and ADU. Refer to the 2022 California Plumbing Code Table 610.4 to
make this determination. Consider revising
Sheet C2 for consistency and avoid confusion during field operations. 4. Sheet
A-5: Submit details that illustrate how roof ventilation air will be allowed to
flow between enclosed rafter bays and exhausted at the upper and lower roof
vents. (CRC R806.1) PC2: This
comment remains. Detailing is not illustrated on A3 as stated in the response
to comment. Please provide. 5. Electrical
Comment: Specify the electrical requirement for the heat pump water heater, as
required by the manufacturer’s specifications/installation manual. PC2: Please
remove reference to “propane” fuel gas at the appliance on E1, E2, and P1. 6. Sheet
S-03: Verify if this project requires structural observation pursuant to CBC
Section 1803. If so, provide a prominent note on the plan, list what is to be
observed, and when field reports shall be submitted to the Building official. PC2: Please
refer to Pg’s. 15, 19 of the Geotechnical Investigation Report, “Project Review
and Construction Monitoring” and “Guidelines for Required Services”. Please provide a
note stating the soils engineer shall provide field observation and testing during
foundation operations. Please ensure Supplemental
Document Form PLG300 is completed and included with the resubmittal package. [End of
Comments] Note: For the
referenced code information, go to http://www.bsc.ca.gov/Codes.aspx and/or
http://www.sccoplanning.com/PlanningHome/BuildingSafety/BuildingCodes.aspx. Resubmittal Requirements: 1) “Complete sets” of plans with revisions clouded, labeled,
and keyed to a revision date list. 2) Written responses referencing revised sheet(s) and/or
detail(s). This plan check list may be copied, and responses written below each
item. 3) Supplemental documents, as required. Resubmittal Information:
http://www.sccoplanning.com/Portals/2/County/Planning/bldg/Re-submittal%20Process%207.21.16.pdf Please be advised that if plan check comments are required
to be addressed leading to a 3rd plan check, additional charges will be added
to your permit fee at an hourly rate. If you have any questions regarding these building plan