Review No:1 Application with civil plans, Stormwater Management Report by
R.I. Engineering dated June 2024 has been received. The following conditions of approval shall be
addressed and items provided prior to building permit issuance:
1)
Provide Final Project Information and
Threshold Form (see CDC Part 3 Appendix A).
Please update this form to include the
impervious areas proposed (sidewalk, walkways, driveway, patios, etc.) at the
project frontage on North Avenue.
2)
Appendix D of Part of the CDC lists all
items that shall be provided by large building permit proposals.
a)
Final Stormwater Management Report with all
required elements:
-
The report shall be updated to describe the
source control measures incorporated in the project design.
-
Provide final detention sizing and flow control
analysis that is consistent with project plans and accounts for new/replaced
impervious areas (on and off site) that bypass the detention mitigation.
-
Provide final retention storage analysis based
on either site specific soil permeability testing or conservative use of
USDA-NRCS soil survey for the depth of the proposed retention facility
(available at: Soil Survey of Santa Cruz County, California (1980)). This may be different for the retention
structure and the design of the landscape strip mitigation as the depths are
different.
-
Provide analysis demonstrating the drainage
facilities proposed for rerouting upstream runoff (proposed swales,
undersidewalk drains, and curb flows along North Ave.) are adequate for design
and overflow storms.
-
Provide analysis utilizing SWM Figures 6 and 7
for the proposed storm drain in North Avenue demonstrating compliance with the
CDC.
b)
Stormwater Management Plan – See Appendix
D for all items required, including:
-
Please provide spot and detail/s for the rock
erosion protection at the end of the swale at Norwest corner.
-
Provide a detail/s describing how the subdrain
from the permeable paver area west of the building will tie into the
detention/retention system.
-
Show inspection and maintenance access locations
for the underground retention/detention system on sheet C-2 and detail 3/C-4.
-
Provide invert elevations in detail 3/C-2 and
update cover notes to be consistent with plan for permeable pavers. Update sheet C-1 to clarify paver extent over
the mitigation area.
-
Please include a note on the plans that states
that no interior drains shall be directed to the storm drain system.
-
Provide details for how retaining walls will
drain – these facilities shall not impact the functionality of the stormwater
mitigation features.
-
Update Detail 7/C-4 to include the requirement
for surface infiltration testing and specify minimum acceptable infiltration rate
with results to be provided to the County inspector prior to project
acceptance.
-
Provide detail and specifications for landscape
strip mitigation consistent with the analysis.
c)
Maintenance
A recorded stormwater facilities maintenance agreement (SWM25B) is
required. Please provide a draft
agreement with attachments for review prior to building permit approval. The
agreement shall include the required map, maintenance schedule, signs of system
failure, etc. per the CDC. The map and
detailed maintenance shall include the offsite inlets, storm drain pipes,
signage, and landscape mitigation strip proposed within the non County
maintained roadways. The agreement shall
include test method and minimum acceptable surface infiltration rate for the
pervious pavement areas and landscape mitigation areas that shall be conducted
at least once a year as well as methods to be used and indication as to when cleaning,
restoration and replacement are required.
The agreement shall include maintenance of the swale and outlet
stability at the Northwest corner of the site.
Given the flow control structure is proposed to be located more than 8
feet below grade provide specific methods to be used to inspect and clean out
orifice as well as the detention/retention chambers. If a vactor truck will be required for
maintenance how will it access the site?
Photo documentation for the rip rap outlet at the NW corner and of the
cleaned and clear orifice will be required each year with the annual
report. If guidance will reference manufacturer
suggested maintenance the maintenance guidelines shall be included in the
recorded document. The agreement shall
include acknowledgement of annual reporting and oversight fee. The final recorded document will be required
prior to building permit final/occupancy.
A hold will be placed on the permit for the final document.
3)
Provide final landscape plans that are
consistent with the final civil plans.
Preliminary plans showed discrepancies regarding surfacing.
4)
Provide review letter from the project
Geotechnical Engineer approving of the final civil grading and drainage plans. The review letter shall specifically approve
the design for consistency with recommendations 10-14 from the 9/10/19
geotechnical investigation.
5)
Public Works staff will inspect the construction
of the drainage related items. Please provide engineer’s estimate for the
construction of the drainage items (there is a 3% inspection fee). A hold will
be placed on the building permit for a preconstruction meeting with the Public
Works Construction Engineer (please call at least 72 hours prior to
construction to schedule the preconstruction meeting at 831.454.2160). A second
hold will be made for approval of the final construction by the Public Works
Construction Inspector.
6)
As-built digital file for all drainage
facilities shall be submitted prior to permit final and occupancy. The
submittal shall contain the following criteria: Projection: State Plane
Coordinate System - California III - Feet Horizontal Datum: NAD 83 Vertical
Datum: NAVD 88 Any CAD is acceptable. AutoCAD is preferred. All changes shall be dated and clouded. For significant field changes change order
permit applications may be required.
7)
Zone 6 impervious area impact fees will be
assessed based on the net increase in permitted impervious areas. These fees will be assessed at building
permit issuance.
|