B-252469_2025-05-09_1st MRS

Revise and harmonize documentation in a comprehensive manner.

If not otherwise noted, each comment refers to CBC 107.2.

Building Review Comments

1.       Accessibility: See AB3002 Notice online. This project is NOT accessibility exempt (CBC Chapter 2, 11B-202.4, DOJ, DSA).  Submit a completed PLG-245 along with the detailed documentation identified on the form, and show all related accessibility compliance upgrades on the plans. If noting on the form that all existing elements meet 2022 code requirements, then show compliance for all such items on the plans. For additional information, see this video explaining Disabled Access Upgrade Requirements for Existing Buildings and Facilities. Review to follow.

2.       Sheet A/C=(A0.2.1, A2.2.2, C1, C2, C3, etc.): Please harmonize architectural and civil for stairs, ramps, guards, handrails, etc. A/C sheets cross reference each other for additional information but do not show essential code compliance requirements. Documentation must clearly show and harmonize related code compliance requirements and reference them in the response letter (e.g. “see x/xx” rather than “see civil”).

3.       Sheet A/C: Please show the elevation heights for finish floor, exterior upper and lower landings at pavement. Revise 1/C2 to specify the number of treads instead of the approximation shown.

4.       Sheet A/C: Show ramp rise compliance; add an intermediate landing if required. The rise for any ramp run shall be 30 inches maximum. CBC 11B-405.6

5.       Sheet A/C: On both sides of the ramp, show details for a curb or guide rail continuous along the length of the ramp. CBC 11B-303.5, 11B-405.9.2

6.       Sheet A/C: Show ramp width clearance compliance between curb and/or guide rails. The clear width of a ramp run shall be 48 inches minimum. CBC 11B-405.5

7.       Sheet A/C: For door 100C, show on the plans a 42 inch or greater strike-side clearance to the top of the ramp run. CBC 11B-405.7.5

8.       Sheet A/C: Detectable warnings. The southern paved area is a “vehicular way”, and the ramp circulation path requires a detectable warning. The bollards shown on 3/A0.2.1 do not alleviate detectable warning requirements, and while detail 8/A0.2.2 is marked “not used,” detectable warnings are required. Show the location, layout with dimensions, and details for a continuous 36” blended transition detectable warning between the required ramp landing and the vehicular way. Detectable warnings are not allowed within the ramp landing. CBC Chapter 2, 11B-250.1ex#1, 11B-247.1.2.5, 11B-302, 11B-405.7.1, 11B-705

9.       Sheet A/C: Detectable warnings. Show on the plans that “Only approved DSA-AC detectable warning products and directional surfaces shall be installed.” CBC 11B-705.3

10.   Item 92/C3: Show code compliance for stair stripes. CBC 11B-504.4.1.

11.   Item 92/C3: Show code compliance for stair nosing. CBC 11B-504.5.

12.   Sheet A/C: Guards are required at the open side of walk surfaces >30-inches above any point within 36-inches of stairs and ramps. Show complete details showing heights and openings. CBC 1015

13.   Sheet A/C: Show and harmonize locations of handrails. Handrails shall be provided on both sides of stairs and ramps. CBC 11B-505.2

14.   Sheet A/C: Show complete details for top and bottom handrail extensions at ramps. CBC 11B-505.10.1

15.   Sheet A/C: Show complete details for top and bottom handrail extensions at stairs. CBC 11B-505.10.2, 11B-505.10.3

16.   Item 92/C3: Show the proposed protruding handrail extensions to be 27-inches maximum above the finish floor or ground. CBC 11B-307.4

17.   Sheet A/C: Show the top of gripping surface height dimension above stairs and ramps. CBC 11B-505.4

18.   Sheet A/C: Show handrail clearance to walls, guards and pilasters. CBC 11B-505.5

19.   Sheet A/C: Show handrail grip size and surface requirements. Show attachment details. CBC 11B-505.7, 11B-505.8

20.   Item 92/C3: Clarify what concrete wall dimension is 8-foot and specify the concrete thickness.

21.   Interior Elevations: Please mark references on the plans showing orientation and drawing numbers.

22.   Interiors: Show requirements for the wall and ceiling finish Class, flame spread index, and smoke developed index. CBC 803.1.2, Table 803.13

23.   Self-service shelving: Please indicate on the plans if the 3-foot aisles serve elements on only one side or both sides. Aisles serving both sides must be 44-inches or larger. Self-service shelves shall be located on an accessible route complying with Section 11B-402. The clear width for aisles shall be 36 inches minimum if serving elements on only one side, and 44 inches minimum if serving elements on both sides. CBC 11B-225.2.2, 11B-403.5.1ex4

24.   Self-service shelving: Storage racks are proposed; complete structural details are required. For a general list of standard rack/storage requirements, see the handout by the Gilroy Storage Rack Guidelines, and provide all required information. SCC does not have an exception for storage racks 5’-9” or less, so anchorage is still required.

25.   Restrooms: The plumbing plans show all new fixtures, piping, concrete floor removed/replaced, a hi/low drinking fountain installed (which must be in alcove), etc. The architectural does not show this scope and shows a fire extinguisher at the fountain location. If a fountain is added, show CBC 11B-211 and 11B-602 compliance. Harmonize documentation and clearly include all work in the project scope and coordinate with comment #1 above. Review to follow.

26.   Restroom Door: Provide door signs. CBC 11B-216.8.1, 11B-703.7

27.   Special Inspections Form PLG240: Required special inspections appear to include epoxy set holdowns, structural welds, guard base welds, etc. The special inspector must be selected from the PLG-240 list of approved agencies. The project Engineer is required to identify applicable CBC special inspections for the project on a completed PLG240 form signed by all parties and incorporated onto the plan sheets. Forms & Publications

28.   Sheet P0.1: Schedule shows WC 1.6 GPF max. Code requires 1.28 max. CPC 411.2

29.   Sheet P0.1: Schedule M.V. remarks references which is not included in the plans.

30.   Sheet P1.0: Seismic design references sheet G1.1 which does is not included in the plans. And refers to details that are required but do not seem to be show for the water heater.

31.   Incomplete Submittal: While some items have been identified, a more comprehensive plan review can only be conducted after submittal of complete drawings, specifications, details and supporting documents. CBC 107

Michael Sotero Certified Plans Examiner - Architect | Tel: 831-454-3249 | michael.sotero@santacruzcountyca.gov

Review No:2

B-252469_2025-07-15_2nd MRS

Revise and harmonize documentation in a comprehensive manner. If not cited below, see CBC 107.2.

#X=previous comment number (previous comment text online: Application Status)

[KK:xxx] = Kamus Keller response

Note: The Civil sheets were not bookmark creating additional review time. Responses often lack clarity of the sheet and/or drawing where revisions are made. Additional review fees are being added to the permit cost.

Building Review Comments

1.      Red: The color red is not allowed. Revise all sheets as required. (e.g. A0.2.1, A1.1, A2.2.1, A4.1, etc.) ePlan User Guide

2.      #1 Accessibility: [KK: The response conveys that no hardship is requested.] Response: Understood, and since the project cost exceeds the maximum valuation threshold, full compliance is mandatory. Please correct the form items C1, C2, and C5 to all show zero. The fountain does not exist and is simply required to be accessible when added; it is not an upgrade. Similarly, the existing entry was already accessible, and the redesigned entry does not contribute toward accessibly upgrades, it is simply a design choice that must be accessible. Since full compliance is being demonstrated, once submitted correctly the form will remain part of the issued documents.

3.      Full compliance is required, show accessible electrical switch and outlet heights. CBC11B-308.1

4.      Sheet A4.1: Clarify that both restrooms must have all-gender signage. California Health and Safety Code Section 118600

5.      Sheet A4.1, Unisex Restroom Doors: Show privacy latch, a maximum operation force of 5 pounds, and all operable parts 34 inches minimum to 44 inches maximum above finished floor. Clarify if closers or spring hinges are used, and specify closing speed requirements. CBC 11B-213.2.1, 11B-404.2.9, 11B-404.2.8

6.      Sheet A4.1: Elevation C show a 3’-4” vertical dimension, clarify intent.

7.      #2, #3, #4 Sheet A/C: [KK: ramp is 28”. Rise shown on elevation 3/A2.2.2.] Response: Drawing 3/A2.2.2 seems to show bottom of landing at -27 inches and C2 shows the bottom of ramp at -29 inches. Harmonize documentation. Previous Comment: Show ramp rise compliance; add an intermediate landing if required. The rise for any ramp run shall be 30 inches maximum. CBC 11B-405.6

8.      #2, #5 Sheet A/C: [KK: This has been added. Handrail design coordinated on both sets.] Response: Please clarify where revisions are made in written responses as previously stated in comment #2. Comment #5 is not about handrails it is about guide rails/curbs. Sheet C2 added a note “far rail will need bottom guide rail: near rail can be attached to the guardrail.” which does not explain requirements nor provide the required drawn details. Provide drawn guide details that clearly demonstrate a 4 inch sphere cannot pass through, a curb must be at least 6 inches above the walking surface at abrupt changes or provide a guide centered between 2 inches and 4 inches, prevent wheel entrapment, provide a continuous and uninterrupted barrier along the length of the ramp and not reduce the ramp width to less than 48 inches clear. Address the previous comment, review to follow. Previous comment: On both sides of the ramp, show details for a curb or guide rail continuous along the length of the ramp. CBC 11B-303.5, 11B-405.9.2

9.      #8 Sheet A/C: Detectable warnings. [KK: The architect’s response differs to civil and detail 8/A0.2.2 remains marked “not used.”] Response: Since this detail is not used, add the following to detail PVMT-98/C3 “Detectable warning surfaces shall be yellow and approximate FS 33538 of SAE AMS-STD-595A.” CBC 11B-705.1.1.3.1

10.   #10 Item 92/C3: [KK: stair stripes requirement note added to stair detail on sheet C3.] Response: Information added shows incorrect stripe width, requires the dimension from nose of step/approach, and stripes must be on the upper approach in addition to treads. “Exterior stairs shall have the upper approach and all treads marked by a stripe providing clear visual contrast. The stripe shall be a minimum of 2 inches wide to a maximum of 4 inches wide placed parallel to, and not more than 1 inch from, the nose of the step or upper approach. The stripe shall extend the full width of the step or upper approach and shall be of material that is at least as slip resistant as the other treads of the stair. A painted stripe shall be acceptable. Grooves shall not be used to satisfy this requirement.” CBC 11B-504.4.1

11.   #2, #12, #13 Sheet A/C: [KK: reference is made to C2 and A2.2.2.] Response: The stairway is confusingly shown differently on drawings and details, and this will affect both the layout and dimensions. Most sheets show the top riser/landing aligned with grid A while A2.2.2 and PMVT-92 show the upper landing extended beyond grid A (see comment below). It does not seem possible to align riser with grid A as the details show risers with a sloped face. Harmonize all documentation. CBC 1015, 11B-505.2

12.   #2, #12, #13 Grids on 2/A2.2.1 and 2/A2.2.2 are labeled D-C-B but should be A-B-C. Harmonize documentation.

13.   #2, #15 Sheet A/C: [KK: top and bottom extension added to stair detail.] Response: The bottom extension must specify the dimension of 1 tread length between the stair nosing and the 1-foot horizontal dimension. The horizontal dimension must be moved to the inside face of the outermost vertical bar to align with code requirements. See comment below CBC 11B-505.10.2, 11B-505.10.3

14.   #2, #15 Sheet A/C: [KK: top and bottom extension added to stair detail.] Response: As commented, the sharp corner shown at the outer extension is not allowed, show a round/smooth transition as required by code. Handrail gripping surfaces and any surfaces adjacent to them shall be free of sharp or abrasive elements and shall have rounded edges. CBC 11B-505.8

15.   #2, #17 Sheet A/C: [KK: notes added to callouts on sheet C2 as well as stair and handrail details C3.] Response: The civil sheets confusingly incorrect terms calling handrails as ‘36” high guardrails.’ Revise notes for C2 stair and ramp, and C3 details to correctly identify handrails and guardrails. CBC 11B-505.4

16.   #2, #17 Sheet A/C: [KK: notes added to callouts on sheet C2 as well as stair and handrail details C3.] Response: As previously commented, 1/C2 obscures handrail with a “METS” mark. Please make legible.

17.   #2, #19 Sheet A/C: [KK: grip size specifications added to detail sheet C3.] Response: As previously commented, show attachment details. Handrail to guardrail and handrail to wall attachments must resist linear load of 50 pounds per foot and concentrated load of 200 pounds in accordance with Section 4.5.1.2 of ASCE 7. CBC 1607.9.1, 1607.9.1.1

18.   #20 Item 92/C3: [KK: The wall is meant to say 8” (thickness) concrete wall, this will be revised.” Response: The detail is not revised to 8-inches; it still says 8-feet. Please address.

19.   #23 Area B shelving: [KK: Shelving located in Parts Area ‘B’ is not self-storage (employee pull only).] Response: Label the Area B as “Employee Work Area.” CBC 11B Chapter 2, 11B-403.5.1 Exception 4, 11B-248.1. 11B-248.2, 11B-203.9, 11B-206.2.8

20.   #23 Area B shelving: [KK: Shelving located in Parts Area ‘B’ is not self-storage (employee pull only).] Response: Area B is an “Employee Work Area” with “Common Use – Interior or exterior circulation paths, rooms, spaces or elements that are not for public use and are made available for the shared use of two or more people.” The aisles do not meet the exception for “work area equipment” and must be “44 inches minimum if serving elements on both sides.” Please address. CBC 11B Chapter 2, 11B-403.5.1 Exception 4, 11B-248.1. 11B-248.2, 11B-203.9, 11B-206.2.8

21.   #24 Shelving: [KK: Fixture calcs and details provide as Supplemental Documentation]. Response: PLG-235 lists “Fixture Calculations” but nothing is bookmarked nor was anything added. Please clarify, review to follow.

22.   #29 Sheet P0.1: [KK: M.V. is noted on sheet P3.0 detail #3.] Response: Sheet P3.0 does not exist. Please revise.

23.   #30 Water Heater, Seismic: [KK: Seismic design was left in by mistake and has been removed.] Response Detail 5/P2.0 “front view” note references “sheet ME1” which does not exist and does not clearly state that strapping is required. As previously commented, water heater seismic strapping is required. Please correct notes and add strapping details to P2.0. CPC 507.2

Michael Sotero Certified Plans Examiner - Architect | Tel: 831-454-3249 | michael.sotero@santacruzcountyca.gov