Projects Under Construction
(Scroll down to view all projects)
EAST CLIFF DRIVE BLUFF PROTECTION PROJECT |
||
Project Location: | East Cliff Drive (between 32nd and 336th Aves and at 41st Ave), Pleasure Point
|
|
Designer: | Sanders & Associates Geostructural Engineering, Inc. (SAGE)
|
|
Lead Agency: | Santa Cruz County Redevelopment Agency in conjunction with the Department of Public Works
|
|
Project Manager: | Melissa Allen
|
|
Construction Manager: | 123 Engineering, Inc.
|
|
Contractor: | Drill Tech Drilling & Shoring, Inc.
|
|
Construction Contract Amt: |
6.7 million
|
|
Est.# of Construction Related Jobs: | Up to 50 |
|
Project Data: |
Bluff stabilization as sculpted soil nail walls between 32nd Ave and 36th Ave and a section of bluff at the end of 41st Ave, including two replacement and one new beach access stairways and beach riprap and rubble removal along the beach. (Blufftop Parkway project to follow after completion of walls.)
|
|
Completion Date: | November 2010
|
|
Completed Work: | Rip Rap & Rubble Removal, new Stairway #1 at 32nd Ave, replacement Stairway #2 at 36th Ave, replacement Stairway #3 at The Hook and bluff walls with shotcrete sculpting and staining.
|
|
Current Work Activities: |
None; this phase of project is completed.
|
|
Project Summary Page: | Click Here |
Completed Bluff Walls from 32nd to 36th Aves
LIVE OAK RESOURCE CENTER PROJECT
This new facility is being built as a model project for the co-location of compatible non-profit human services organizations in a County-owned building. This will provide these non-profits with a stable base upon which to build their operations; delivering service directly to the local community. The tenant agencies will be the Live Oak Family Resource Center (part of Community Bridges) and the headquarters of the Volunteer Centers of Santa Cruz County.
Project Location: |
1740 17th Avenue, just north of Capitola Road, across from Ferrell's Donuts. |
|
|
|
|
Architect: |
Jacquie Low, of Boone Low Ratliff Architects, Santa Cruz |
|
|
|
|
Lead Agency: |
Redevelopment Agency, in cooperation with the Human Services Department. |
|
|
|
|
Project Manager: |
Robert Hambelton Redevelopment Agency |
|
|
|
|
Construction Manager: |
Gilbane Building Company |
|
|
|
|
Contractor: |
Bogard Construction, Inc., |
|
|
|
|
Construction Contract Amt: |
3.3 million |
|
|
|
|
# of Construction Jobs: |
Up to 40 on any given day |
|
|
|
|
|
|
|
|
|
|
Completion Date: |
December 2010 |
|
|
|
|
Completed Work: |
Rough grading and compaction, foundations, steel and wood framing, in-floor hot water heating systems, the concrete slab, rough framing, electrical, and plumbing, roofing, siding, interior finishes, painting, paving and landscaping.. |
|
|
|
|
Current Work Activities: |
Flooring, art installation, and final touchup. |
|
Project Summary Page: |
|
|
SOQUEL AVENUE IMPROVEMENT PROJECT
|
||
Project Location: |
Soquel Avenue (between Soquel Dr. and 17th Ave.), Live Oak
|
|
Designer/Engineer: |
County of Santa Cruz, Department of Public Works (DPW)
|
|
Lead Agency: |
DPW in conjunction with the Santa Cruz County Redevelopment Agency (RDA)
|
|
Project Manager: |
Melissa Allen, RDA
|
|
Construction Inspector: |
Chad Hamann, DPW
|
|
Contractor: |
Pavex Construction
|
|
Construction Contract Amt: |
$731,000
|
|
Est. Number of Construction Related Jobs: |
Up to 20
|
|
Project Description: |
Roadway and roadside improvements include a second westbound travel lane between Highway 1 on/off ramps and 17th Avenue and sidewalks, bike lanes, curbs, gutters and drainage improvements along the south side of Soquel Avenue. The project also includes new street trees and landscaping for this "gateway" to Live Oak.
|
|
Completion Date: |
June 2011
|
|
Completed Work: |
PG&E, Cable & AT&T relocated existing utilities including in-ground boxes, poles and some overhead wires to accommodate project, roadside improvements with sidewalk, curb and gutter, and drainage improvements along the south side of the road, landscape bulb-outs and other improvements, road paving and striping.
|
|
Current Work Activities: |
None; project is completed.
|
|
Project Summary Page: |
|
Before Construction
During Construction
After Construction