East Cliff Drive Parkway 
and Bluff Protection Project
        	  Location: Pleasure Point Area of East Cliff Drive between 32nd Avenue and 41st Avenue
Project Manager: Melissa Allen 
  
Background and History: Failure of the cliffs along East Cliff Drive occurred periodically over the past several decades. It became clear that continued failures would ultimately undermine the road, threaten vehicle access for residents, limit pedestrian and bicycle access to the cliff and beach, and sever major underground utility lines. The County and area residents were able, through the assistance of then-Congressman Leon Paneta, to secure funding for a Corps of Engineers study of cliff stability issues in the area. That study, completed in 1994, concluded that cliff stabilization was critically needed and qualified for federal funding.
  In the meantime, significant additional cliff failures occurred in early  1994, resulting in the need to restrict traffic on East    Cliff Drive to one-way and to repair the bluff and  road near Larch Lane.  Because of the problems this restriction  caused, a citizens’ task force was established to evaluate the issues further.  The consensus was, given the scenic and  recreational attraction of the area for the entire community as well as coastal  visitors, that walking and bicycling along the cliff should be made as safe and  enjoyable as possible; that one-way traffic should be maintained with vehicular  traffic shifted as far away as possible from the cliff edge; and that overall  traffic circulation should encourage through-traffic to remain on East Cliff  Drive.  Unfortunately, these improvements  could not be constructed without first stabilizing some sections of the coastal  bluff.  Based on the task force  recommendations, the Board of Supervisors directed staff in 1995 to pursue  funding for a cliff stabilization project to facilitate the community’s future  vision for the area.
  While exploring options for protecting and enhancing public use of this  section of East Cliff Drive, staff has focused efforts on providing a generous  public walkway and bike path along the road and stabilizing the underlying  cliffs.  The wall portion of the project  (between 32nd Avenue and 36th Avenue, and at the end of 41st Avenue) includes  the construction of two colored, sculpted, concrete "soil-nail" walls, two new access stairways to the beach, and the removal of concrete rubble on  the beach.  The upper bluff improvements,  which are a separate component, will consist of a pedestrian path, bicycle  path, landscaping, safety railings, and improvements to the small, neighborhood  park at 32nd Avenue.
  After the preliminary designs were completed and presented to the community  in December of 2000, an application for a Development Permit for the bluff top  improvements was submitted to the Planning Department. As part of the permit  process a joint Environmental Impact Statement/Environmental Impact Report (EIS/EIR)  was prepared for both the bluff top and the cliff stabilization work.
  An application for a Consistency Determination to the California Coastal  Commission by the US Army Corps of Engineers for the stabilization work  resulted in an objection by the Commission and Final Findings were adopted at  the January 2004 meeting.  Meanwhile,  repairs to three cribwalls in the area were completed in the fall of 2004 under  an emergency permit (See East Cliff Crib Walls Emergency Repair Work).
  After some project revisions and additions to the EIR,  the County Board  of Supervisors approved the project Development Permit application on March 20, 2007 and certified the  Revised Final EIS/EIR.  The Final  Environmental Impact Statement and Report can be viewed online at the Planning  Department website http://www.sccoplanning.com/pdf/env/eirecliffseawall/toc.htm.
  The project was presented to the California Coastal Commission at its  December 2007 meeting and received unanimous approval for the County's permit  application.  The Commission staff report  can be viewed at their website under the December 13, 2007 hearing date, Items 13a and 14a by  visiting the following web location http://www.Coastal.ca.gov/meetings/mtg-mm7-12.html.   The Redevelopment Agency and Public  Works have obtained all required permits for this project.
This project consists of two phases of work. The first phase has been completed and includes bluff stabilization with sculpted soil nail walls between 32nd Avenue and 36th Avenue and a section of bluff at the end of 41st Avenue, two replacement stairways and one new beach access stairway, and beach riprap and rubble removal. The second phase now under construction includes a new pedestrian/bicycle path up to 16' wide, additional landscaping and replacement parking for the entire section of the one-way road between 32nd Avenue and 41st Avenue, and a public restroom for the Pleasure Point Park. These improvements are planned as part of the proposed Monterey Bay Sanctuary Scenic Trail as it proceeds through the Live Oak area between the cities of Santa Cruz and Capitola.
  Project Status:
  Phase 1 - Construction of the  bluff protection structure between 32nd and 36th Avenues and at the Hook has  been completed.  Construction of the  bluff protection portion of the project began in early summer 2009 and was  completed in November 2010.  That  construction included removal of riprap and concrete rubble from the beach from  Pleasure Point Park to 36th Avenue and at the Hook; new beach access stairs at  the park at 32nd Avenue & Pleasure Point Drive which opened in December  2009; construction of replacement stairs near 36th Avenue which were completed  mid 2010, and replacement stairs at the Hook which were opened to the public in  October 2010.  To  view bluff construction site plans click here.  For more information and photos see Projects Under  Construction.
  
  Phase 2 - Roadway and pedestrian improvements are following now that the  bluff stabilization work is complete.   Local consultants Whitson Engineers prepared design plans for the  parkway portion of the project.  Two  additional Community Meetings were held in spring 2009 and fall 2010 to discuss  the Pleasure Point   Park design, Monterey Bay National  Marine Sanctuary interpretive exhibit, to present the latest Parkway plans, get  input on safety railing fence options, and discuss the project schedule.  Click on the following links to view the Parkway  Concept Design and Park  Concept Exhibits.  Though there will  be new improvements at the park including a public restroom with outdoor rinse  showers, all of the existing community placed art features will be retained  and reinstalled with the new design and replaced after construction is complete.  The construction contract for the parkway  portion of the project was awarded by the Board of Supervisors in May 2011 to Granite  Rock Company, Pavex Construction Division.  Notifications for the start of construction were  sent out in late May and early June.  Construction  will begin in July 2011 and is expected to be complete in the summer of  2012.
  To view construction plans, click here.
  Also, for a current rendering of the Pleasure Point Park, please click here.
Click here to view Start of Construction Notice.
After considerable public discussion in the fall of 2010 regarding the final designs for the safety railings, which are necessary in places where the pedestrian pathway is directly adjacent to the steep bluff cliff, the Redevelopment Agency posted simulations of two alternative railing styles on this webpage for public input. Of the two final style options, more members of the public preferred the railing with a 42" wood frame design with thin vertical steel bar inserts. In locations where safety railings are not necessary, traditional wood split rail fencing will be used.

  As the contractor begins this project, Supervisor John Leopold will be hosting a community meeting this Monday, August 8th, at the Simpkins Swim Center starting at 7 pm to review with the community the work that will be done over the coming months.
  
For questions, please call Melissa Allen, Project Manager, at 454-2280, or Joel LaCagnin at 454-2160.
        


















